Enter your address

10:43PM September 21, 2021

Otis Duck

They have installed the lines running to the poles and currently have them hanging there. What are the next steps until being internet ready?

User Avatar

12:04PM September 22, 2021

Nick Gutierrez
Hi, Otis. There are several steps that will have to be completed before being internet ready. This includes constructing the main line, putting a service drop to the home, placing a NID (small gray box) to make a connection, splicing the fiber at your home, and then testing the light. Once we have received word that the home is ready to be connected, our team will reach out to you and schedule it at your convenience. Thank you for your support of Gibson Connect!