South Fulton area update

User Avatar

8:59AM February 21, 2022

Sarah Williams
Hi, Jimmy. We have crews working throughout the South Fulton zone, but it will be a little longer before connections are ready to begin. As of now, we expect homes to start being connected in late May or June, and hope to have the majority of the area completed by late summer. There are several variables that could impact this timeline such as material availability, contractor staffing, and weather. We will continue to update our members of any large changes we expect. Thank you for your support of Gibson Connect!