Enter your address

5:13PM August 15, 2022

Pete Hudson

Is there a timeline for Friendship/Crockett Mills area? I have noticed the construction and the Fiber Line has been run to my house. Just curious. Thanks Pete

User Avatar

8:00AM August 16, 2022

Dawn Jewell
Hi Pete, We are currently splicing the mainline fiber in the Friendship area. We also have crews placing service drops and beginning to splice individual locations. As of now, we are anticipating most of this zone to be completed by late fall. We appreciate your patience and support of Gibson Connect. We look forward to serving you.