Jenni Rachels Admin

Hello, Jeremy. We have been working in the Rutherford substation. Specifically, we have installed the new substation house, provided electric power to the house and installed a backup generator. Currently, we’re working to install the OLT electronic equipment which will light the fiber. (The light provides the internet data.) Our contractors have completed most of the middle-mile overhead construction. Next they will engineer the fiber splicing design. Once this part of the engineering design is completed, it will be ready to be spliced. After the splicing is completed, we will run the service drops, and finally we will do the in-premise installations. It’s still too early to provide details about the timing, but we will keep you posted. Have a great weekend!