Hello, Misty. We've started construction of the fiber distribution system in Tiptonville. We hope to complete installations in the Medina/Three Way zones this summer and in the Dyer zone in late summer or early fall. Next, we will begin splicing, putting in service drops and doing installations in Ridgely, Tiptonville and Samburg. When we get your service drop built, we will call the telephone number you have provided to schedule your installation. We appreciate your support!
9:49AM May 29, 2019
Jenni Rachels Admin
Hello, Misty. We've started construction of the fiber distribution system in Tiptonville. We hope to complete installations in the Medina/Three Way zones this summer and in the Dyer zone in late summer or early fall. Next, we will begin splicing, putting in service drops and doing installations in Ridgely, Tiptonville and Samburg. When we get your service drop built, we will call the telephone number you have provided to schedule your installation. We appreciate your support!