Enter your address

4:26PM December 08, 2020

JACQUELYN MOODY

We are on Mt Zion rd. Our yard is marked with orange paint and there have been crews in the area trenching. When should we expect to be connected?

User Avatar

8:21AM December 09, 2020

Sarah Williams
Hi, Jacquelyn. I see that your service drop has been completed, but crews have not yet spliced the fiber. We are hopeful to have the majority of this zone connected by the end of the year. Contractors are working throughout the area on several different steps, and trying to get members connected as quickly as they can. Please continue to be patient with us as we work to bring this service to all of our eligible members. We appreciate your support of Gibson Connect, and look forward to serving you, soon!