Fulton Reaches Participation Goal!
12:05PM October 06, 2020
Wow! Our consumer-members in the Fulton Zone have really stepped up! This zone has now reached its participation goal, moving it a step closer to high-speed, fiber-based internet service! Zones that we’re currently working on are Woodland Mills, Obion, Rutherford, Kenton, Newbern and Troy. Next in line will be our Alamo, Clinton and Fulton zones.
Engineering for the Fulton Zone is expected to begin in the summer of 2021. Next, we’ll order materials and begin the construction process. We expect to begin construction next fall. If all goes as planned, we hope to be connecting our first Fulton Zone members in the late fall of 2021 or early winter of 2022.
The Bells zone at 96% is very close to
also reaching its participation goal and needs just 17 more registrants.
South Fulton is at 82% and needs just 64 more members to register. If you have
not yet registered, do it today at join.gibsonconnect.com. Please encourage
your friends and neighbors to register, too!