Sarah Williams
Candace, as soon as our team has received a light reading for your location, they will be calling you to schedule the installation. Sometimes the box is on the house before the fiber is spliced, so it could still be a little bit before it is ready for connection. I do see that your service drop has been placed, but the fiber still needing to be spliced. Once this has been completed, we will be giving you a call!
12:54PM June 20, 2022
Dana Lawrence
Any update on East Grace Roach Rd in South Fulton, TN. The box has been mounted to the side of the house. Contractor said we would be contacted about our inside equipment.
Sarah Williams
Hey, Dana. I can see that your service drop is completed, but the fiber has not been spliced to the home. We have crews working on splicing both the main line fiber and fiber to the home. As soon as we get a light reading for your location, our team will be calling to schedule your installation. We are expecting connections to begin by the end of the month, and to have the majority of the zone largely completed by late summer. Thank you for your support of Gibson Connect!
11:48AM June 20, 2022
Ben Rudy
Now that the grant has been awarded from KY, how long before the additional buildout and installations of residential service in the Hickman Zone. I am on KY 1128, and have been looking at doing some swapping on satellite options. but I do not want to sign a new contract if Gibson will be available within a year or less.
Sarah Williams
Hi, Ben. We anticipate being able to start construction mid-July, after receiving the grant parameters and signing the grant contract. We will communicate more details about the buildout soon. We are very excited that we have been awarded this grant funding, but as of now, we do not have specific dates for individual zones. As soon as we have updates regarding timeframes, we will communicate them. Thank you for your support of Gibson Connect!
Sarah Williams
Hi, Rubi. We currently have crews in the area working on placing service drops and splicing both main line fiber as well as fiber at individual locations; we are expecting connections to begin by the end of June. We have a little over 400 locations to complete in the zone, but as of now, anticipate the area to be largely finished by late August or early fall. Again, we appreciate your support of Gibson Connect and look forward to serving you!
8:19PM June 19, 2022
Jason Duncan
What’s the timeline on getting service up and running on Flippen Drive between South Fulton, and Tennessee? The contractors just buried the fiber in my yard last week.
Sarah Williams
Hi, Jason. Crews are working throughout the South Fulton zone placing service drops, and splicing both the main line fiber as well as individual locations. We are anticipating connections to begin in the next couple of weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
8:21PM June 19, 2022
Jason Duncan
I meant Union City, not Tennessee.
10:39PM June 17, 2022
David sutton
Can I purchase a device to extend my Wi-Fi to be able to connect when in my shop approximately 125 feet from the router?
David sutton
Yes, please have someone contact me cell number 731-345-9109
8:41AM June 20, 2022
Sarah Williams
Hi, David. We do have extenders you can rent monthly, however, I would recommend you speaking to one of our Network Technicians to see if that would even be feasible for your question. Depending on several factors, including distance, it may not work to have an extender. I can have one of them reach out to you if you would let me know your best contact number, and we will figure out the best route to help you move forward!
1:12PM June 17, 2022
Candace Dutton
Hi when will i get an update I live at 4109 US Highway 45 W Kenton TN thanks
Sarah Williams
Hi, Candace. I see that your registration was completed just a few days ago, so we are estimating 2-3 weeks to complete the construction and have you ready for connection. Kenton is a zone that we have already completed, so our crews will come in and run the service drop, splice the fiber and place the NID on the side of the home; as soon as we get a light reading for your location, we will call and get your in-home install scheduled. Thank you for your support of Gibson Connect!
12:02AM June 15, 2022
Candace Riggins
Curious if/when your services will be available to my area. Adams street in Newbern. It shows Newbern is completed but still says unavailable to my address.
Sarah Williams
Hi, Candace. We are only allowed to service the locations that receive their electric service from Gibson EMC. It looks like Adams Street is in town Newbern, and does not fall in our service area. Because of this, we are not able to service your location with Gibson Connect. We appreciate your interest, and thank you for asking!
1:05PM June 14, 2022
Chase Foster
Looking for an update for our address. We are in the far corner of the Bells zone. Is the Bells zone still under construction? ETA spring '22?
Thanks
Sarah Williams
Hi, Chase. We have a little over 50 service drops remaining in the Bells zone, and crews are working as quickly as possible to get them completed and spliced. Weather permitting, we are estimating to have the Bells zone completed in the next 2-3 weeks. We appreciate your support and continued patience as we work to complete the Bells zone, and surrounding areas!
11:58AM June 13, 2022
Melissa Conner
Can you please give me an update for my address? We have seen additional work being done in our neighborhood and our neighbors around us, but nothing additional has been done at our address. Thanks.
Sarah Williams
Hi, Melissa. I can see that your service drop is under construction, and the fiber will have to be spliced to the home before it will be ready for connection. Crews are working throughout the South Fulton zone placing service drops, and splicing both the main line fiber as well as individual locations. We are anticipating connections to begin in the next few weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
11:44AM June 13, 2022
Lexi Matheny
Can you give an update on Clinton KY?
Sarah Williams
Hi, Lexi. Unfortunately, we still have no new updates regarding grant funding from the state. We are looking at every available option, and as soon as we have information to share, we will update our members. We ask for your patience as we continue to look at ways to build as economically as possible!
2:07PM June 09, 2022
Jared Willcutt
Can you give me an update on my address? Our lines have already been spliced and was told that the next step is installation but we haven't heard from anybody to schedule a date. The neighbor has already gotten their installation date.
Sarah Williams
Hi, Jared. I apologize for the delayed response. I am not showing that we have a light reading for your location, or anywhere on your road. We have crews that are working on splicing both the main line fiber, and have just started splicing individual locations. We are hoping for connections to begin in the next couple of weeks, by the end of June. Once we receive a light reading for your location, we will be calling you to set-up your installation. We appreciate your support of Gibson Connect, and look forward to serving you!
3:18PM June 09, 2022
Jared Willcutt
6464 KNOX DANIEL ROAD UNION CITY, TN 38261
1:54PM June 09, 2022
MaryBeth Pickering
Any update for my address? Last people out here said we were ready to go and should expect a call in about 2 weeks to schedule connection. That has been over a month ago.
Sarah Williams
Hi, MaryBeth. I apologize for the confusion; the contractors have been asked not to provide a two-week timeline for connections, because they often do not know the schedule of where the splicing crews are located. I can see that your service drop has been placed, and the fiber needs to be spliced to the home before it will be ready for connection. Crews are working throughout the South Fulton zone to splice both the main line fiber, as well as individual locations. We are anticipating connections to begin in the next few weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
Sarah Williams
Hi, Antonio. We received the registration at the beginning of June, and because crews had already moved out of the area, it will take a few weeks to get it installed and ready for connection. It looks like the service drop is pending, and they will get it placed as soon as possible. Once the fiber has been spliced, we will call you to get the installation scheduled.
7:49PM June 06, 2022
Nan Singleton
My tv has been out all day..when will it be back in service..
1544 lanes ferry rd Newbern.tn
7313770228
Sarah Williams
Hi, Nan. We were not aware of any issues that were taking place with our TV service yesterday, so I apologize for the issues that you've had. If you are still experiencing problems, please give us a call at 731.562.6001 and we will be happy to take a look. Thank you for being a Gibson Connect subscriber!
Terrance Spicer
Great news, Appreciate it very much.
8:32AM June 03, 2022
Sarah Williams
Hi, Terrance. I spoke with our team yesterday regarding your location, and it was scheduled to be spliced either yesterday or this morning. I will ask them to let me know when it has been completed, so that we can reach out and schedule your install as soon as possible. I apologize for all of the confusion with your home; we are getting it taken care of ASAP!
9:48AM June 01, 2022
Antonio Rodriguez
yea i’m waiting on 1455 martin drive it’s right beside my other house that’s connected
Sarah Williams
Hey, Antonio. I apologize for the delay in responding. It looks like you just got this address registered earlier this week, so it could be up to four weeks before we get it completed. The majority of crews have moved out of the area, so we will have another one that will come in and complete the service drop and then get it spliced for connection. The wet spring weather has pushed us back a bit on underground service drops, but we will have it ready as quickly as possible. Thank you for your continued support of Gibson Connect!
Sarah Williams
Hi, Jimmy. Your service drop is completed, and crews are working on the splicing of the mainline fiber. We have not yet started splicing at individual locations, but anticipate that to begin in the next few weeks once the mainline splicing has been completed. Connections should start by the end of June, and we are still anticipating the majority of the zone to be completed by late summer. We appreciate your continued support and patience as we build the South Fulton area!
3:51PM May 31, 2022
Antonio Rodriguez
Can i get an update on my address
Sarah Williams
Hi, Antonio. I'm showing that your address has been connected and has service. If this is not correct, please give us a call at 731.562.6001. If there is a secondary address you are waiting on, please let us know what it is and we will be able to provide you with an update. Thank you!
10:46AM May 22, 2022
Gail McConnell
You website is the most difficult unfriendly site I have seen in years. It takes a computer degree to figure out how to PAY MY BILL ON LINE. You folks do know this is northwest Tn not Berkeley Ca. right?
Sarah Williams
Hi, Gail. We apologize for the issues you've had trying to pay your bill online. If you have not created an account, we will be happy to help you do that. Please contact us at 731.562.6000 and one of our Member Service Representatives will be glad to assist you. We are glad you're a Gibson Connect subscriber!
9:20PM May 13, 2022
Mack P
I believe Kentucky has passed with emergency status for rural internet. When that will happen and how much less will the cost be from Gibson's original quote???? Because it was posted by Gibson Connect even though Fulton Zone reached its required "subscribers" they stopped work for Kentucky ZONES to have a lower cost!!!!!! Since according to Gibson Connect the Fulton zone should already have their internet SERVICE !!!!!!
Sarah Williams
Mack, while high-speed broadband is essential to our rural service area, applying for grants and trying to reduce costs to our members is also important to us. We have applied for grant funding whenever possible. Following the announcement of the broadband grants in Kentucky, we felt that it was in our members' best interest to apply for and try to attain grant dollars for the buildout in our Kentucky area. At this time, we are awaiting results from the state before we move forward. We appreciate your patience and support, and we look forward to serving you.
5:04PM May 12, 2022
MaryBeth Pickering
Any idea on when we will be connected? We have had two different crews out one hooking the box up at our house and another with the line.
Dawn Jewell
MaryBeth, there are several steps that will have to be completed before your home is ready for internet. This includes constructing the main line fiber which is happening at this time in your area, putting a service drop to your home, placing a NID (small gray box) to make a connection, splicing the fiber at your home, and then testing the light. Once we have received word that the home is ready to be connected, our team will reach out to you and schedule it at your convenience. Thank you for your support of Gibson Connect!
8:12AM May 13, 2022
MaryBeth Pickering
3705 Church Rd Union City, TN
7:56AM May 13, 2022
Dawn Jewell
Hi, MaryBeth. Please provide me with your address so I can check on this for you. Thanks.
7:20AM May 12, 2022
Larry Clark
Can you give an connection update for 677 Lower Jackson Rd, Bells? Thanks.
Larry Clark
Hello Sarah. Thanks for the quick response. One of your team was by here this afternoon and looked over the layout. He was very service focused!
9:13AM May 12, 2022
Sarah Williams
Hey, Larry. There was a bit of a set-back with your address, but I have spoken with our team and we should have your address ready to connect in the next 7-10 days. There are a couple of homes on Lower Jackson Road that we are working to finish; barring any unforeseen circumstances in the next few days, we expect to have you up and going in the next couple of weeks. Thank you for your patience and continued support of Gibson Connect!
8:43PM May 11, 2022
Richard Parham
Wondering when service will be connected at 9893 McConnell rd?
Sarah Williams
Hi, Richard. At this time, we are anticipating connections to begin in the South Fulton zone sometime in June, and the majority to be largely connected by late summer. Of course, there are factors that can impact this timeline such as weather, contractor staffing and materials availability. We appreciate your support of Gibson Connect and look forward to serving you!
9:12PM May 10, 2022
Christian Comer
I had a concern about why my ping has gone up to over 100+ on all sites. I've restarted my router but my ping is still over 100+ consistently usually I get a solid 20 but all day today its been over 100.
Sarah Williams
Hi, Christian. If you are still experiencing issues, please call us at 731.562.6001 and one of our technical support staff will be able to take a look at your account. Thank you for being a Gibson Connect subscriber!
12:23AM May 11, 2022
Christian Comer
Seems to be working normally except the only site pinging over 100 ping is google now everything else seems to be normal.
1:51PM June 20, 2022
Candace Dutton
So after the outside box is connected and on the side of the house , when will i expect a call for the inside service thanks again!
3:56PM June 20, 2022
Candace Dutton
Okie dokie thank you kindly!
3:33PM June 20, 2022
Sarah Williams
Candace, as soon as our team has received a light reading for your location, they will be calling you to schedule the installation. Sometimes the box is on the house before the fiber is spliced, so it could still be a little bit before it is ready for connection. I do see that your service drop has been placed, but the fiber still needing to be spliced. Once this has been completed, we will be giving you a call!
12:54PM June 20, 2022
Dana Lawrence
Any update on East Grace Roach Rd in South Fulton, TN. The box has been mounted to the side of the house. Contractor said we would be contacted about our inside equipment.
3:30PM June 20, 2022
Sarah Williams
Hey, Dana. I can see that your service drop is completed, but the fiber has not been spliced to the home. We have crews working on splicing both the main line fiber and fiber to the home. As soon as we get a light reading for your location, our team will be calling to schedule your installation. We are expecting connections to begin by the end of the month, and to have the majority of the zone largely completed by late summer. Thank you for your support of Gibson Connect!
11:48AM June 20, 2022
Ben Rudy
Now that the grant has been awarded from KY, how long before the additional buildout and installations of residential service in the Hickman Zone. I am on KY 1128, and have been looking at doing some swapping on satellite options. but I do not want to sign a new contract if Gibson will be available within a year or less.
12:17PM June 20, 2022
Sarah Williams
Hi, Ben. We anticipate being able to start construction mid-July, after receiving the grant parameters and signing the grant contract. We will communicate more details about the buildout soon. We are very excited that we have been awarded this grant funding, but as of now, we do not have specific dates for individual zones. As soon as we have updates regarding timeframes, we will communicate them. Thank you for your support of Gibson Connect!
9:04AM June 20, 2022
Rubi Cobb
Update 1655 East Rd Friendship
2:36PM June 20, 2022
Sarah Williams
Hi, Rubi. We currently have crews in the area working on placing service drops and splicing both main line fiber as well as fiber at individual locations; we are expecting connections to begin by the end of June. We have a little over 400 locations to complete in the zone, but as of now, anticipate the area to be largely finished by late August or early fall. Again, we appreciate your support of Gibson Connect and look forward to serving you!
8:19PM June 19, 2022
Jason Duncan
What’s the timeline on getting service up and running on Flippen Drive between South Fulton, and Tennessee? The contractors just buried the fiber in my yard last week.
8:42AM June 20, 2022
Sarah Williams
Hi, Jason. Crews are working throughout the South Fulton zone placing service drops, and splicing both the main line fiber as well as individual locations. We are anticipating connections to begin in the next couple of weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
8:21PM June 19, 2022
Jason Duncan
I meant Union City, not Tennessee.
10:39PM June 17, 2022
David sutton
Can I purchase a device to extend my Wi-Fi to be able to connect when in my shop approximately 125 feet from the router?
1:00PM June 20, 2022
David sutton
Yes, please have someone contact me cell number 731-345-9109
8:41AM June 20, 2022
Sarah Williams
Hi, David. We do have extenders you can rent monthly, however, I would recommend you speaking to one of our Network Technicians to see if that would even be feasible for your question. Depending on several factors, including distance, it may not work to have an extender. I can have one of them reach out to you if you would let me know your best contact number, and we will figure out the best route to help you move forward!
1:12PM June 17, 2022
Candace Dutton
Hi when will i get an update I live at 4109 US Highway 45 W Kenton TN thanks
10:39AM June 19, 2022
Candace Dutton
Thanks so much!
4:40PM June 17, 2022
Sarah Williams
Hi, Candace. I see that your registration was completed just a few days ago, so we are estimating 2-3 weeks to complete the construction and have you ready for connection. Kenton is a zone that we have already completed, so our crews will come in and run the service drop, splice the fiber and place the NID on the side of the home; as soon as we get a light reading for your location, we will call and get your in-home install scheduled. Thank you for your support of Gibson Connect!
12:02AM June 15, 2022
Candace Riggins
Curious if/when your services will be available to my area. Adams street in Newbern. It shows Newbern is completed but still says unavailable to my address.
8:51AM June 15, 2022
Sarah Williams
Hi, Candace. We are only allowed to service the locations that receive their electric service from Gibson EMC. It looks like Adams Street is in town Newbern, and does not fall in our service area. Because of this, we are not able to service your location with Gibson Connect. We appreciate your interest, and thank you for asking!
1:05PM June 14, 2022
Chase Foster
Looking for an update for our address. We are in the far corner of the Bells zone. Is the Bells zone still under construction? ETA spring '22? Thanks
8:49AM June 15, 2022
Chase Foster
Thanks for the detail!
4:54PM June 14, 2022
Sarah Williams
Hi, Chase. We have a little over 50 service drops remaining in the Bells zone, and crews are working as quickly as possible to get them completed and spliced. Weather permitting, we are estimating to have the Bells zone completed in the next 2-3 weeks. We appreciate your support and continued patience as we work to complete the Bells zone, and surrounding areas!
11:58AM June 13, 2022
Melissa Conner
Can you please give me an update for my address? We have seen additional work being done in our neighborhood and our neighbors around us, but nothing additional has been done at our address. Thanks.
4:10PM June 13, 2022
Sarah Williams
Hi, Melissa. I can see that your service drop is under construction, and the fiber will have to be spliced to the home before it will be ready for connection. Crews are working throughout the South Fulton zone placing service drops, and splicing both the main line fiber as well as individual locations. We are anticipating connections to begin in the next few weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
11:44AM June 13, 2022
Lexi Matheny
Can you give an update on Clinton KY?
4:08PM June 13, 2022
Sarah Williams
Hi, Lexi. Unfortunately, we still have no new updates regarding grant funding from the state. We are looking at every available option, and as soon as we have information to share, we will update our members. We ask for your patience as we continue to look at ways to build as economically as possible!
2:07PM June 09, 2022
Jared Willcutt
Can you give me an update on my address? Our lines have already been spliced and was told that the next step is installation but we haven't heard from anybody to schedule a date. The neighbor has already gotten their installation date.
9:49AM June 13, 2022
Sarah Williams
Hi, Jared. I apologize for the delayed response. I am not showing that we have a light reading for your location, or anywhere on your road. We have crews that are working on splicing both the main line fiber, and have just started splicing individual locations. We are hoping for connections to begin in the next couple of weeks, by the end of June. Once we receive a light reading for your location, we will be calling you to set-up your installation. We appreciate your support of Gibson Connect, and look forward to serving you!
3:18PM June 09, 2022
Jared Willcutt
6464 KNOX DANIEL ROAD UNION CITY, TN 38261
1:54PM June 09, 2022
MaryBeth Pickering
Any update for my address? Last people out here said we were ready to go and should expect a call in about 2 weeks to schedule connection. That has been over a month ago.
9:43AM June 13, 2022
Sarah Williams
Hi, MaryBeth. I apologize for the confusion; the contractors have been asked not to provide a two-week timeline for connections, because they often do not know the schedule of where the splicing crews are located. I can see that your service drop has been placed, and the fiber needs to be spliced to the home before it will be ready for connection. Crews are working throughout the South Fulton zone to splice both the main line fiber, as well as individual locations. We are anticipating connections to begin in the next few weeks, by the end of June. Some of our crews are still working to finish up the Troy zone, and then will be coming over to help get the South Fulton zone completed. We appreciate your support of Gibson Connect, and look forward to serving you!
12:48PM June 07, 2022
Antonio Rodriguez
update for 1455 martin dr?
9:38AM June 13, 2022
Sarah Williams
Hi, Antonio. We received the registration at the beginning of June, and because crews had already moved out of the area, it will take a few weeks to get it installed and ready for connection. It looks like the service drop is pending, and they will get it placed as soon as possible. Once the fiber has been spliced, we will call you to get the installation scheduled.
7:49PM June 06, 2022
Nan Singleton
My tv has been out all day..when will it be back in service.. 1544 lanes ferry rd Newbern.tn 7313770228
9:23AM June 07, 2022
Sarah Williams
Hi, Nan. We were not aware of any issues that were taking place with our TV service yesterday, so I apologize for the issues that you've had. If you are still experiencing problems, please give us a call at 731.562.6001 and we will be happy to take a look. Thank you for being a Gibson Connect subscriber!
12:49PM June 02, 2022
Terrance Spicer
Update???
2:27PM June 03, 2022
Terrance Spicer
Great news, Appreciate it very much.
8:32AM June 03, 2022
Sarah Williams
Hi, Terrance. I spoke with our team yesterday regarding your location, and it was scheduled to be spliced either yesterday or this morning. I will ask them to let me know when it has been completed, so that we can reach out and schedule your install as soon as possible. I apologize for all of the confusion with your home; we are getting it taken care of ASAP!
9:48AM June 01, 2022
Antonio Rodriguez
yea i’m waiting on 1455 martin drive it’s right beside my other house that’s connected
3:51PM June 02, 2022
Sarah Williams
Hey, Antonio. I apologize for the delay in responding. It looks like you just got this address registered earlier this week, so it could be up to four weeks before we get it completed. The majority of crews have moved out of the area, so we will have another one that will come in and complete the service drop and then get it spliced for connection. The wet spring weather has pushed us back a bit on underground service drops, but we will have it ready as quickly as possible. Thank you for your continued support of Gibson Connect!
6:46PM May 31, 2022
Jimmy Sturgis
Update on my address please
9:32AM June 01, 2022
Sarah Williams
Hi, Jimmy. Your service drop is completed, and crews are working on the splicing of the mainline fiber. We have not yet started splicing at individual locations, but anticipate that to begin in the next few weeks once the mainline splicing has been completed. Connections should start by the end of June, and we are still anticipating the majority of the zone to be completed by late summer. We appreciate your continued support and patience as we build the South Fulton area!
3:51PM May 31, 2022
Antonio Rodriguez
Can i get an update on my address
8:33AM June 01, 2022
Sarah Williams
Hi, Antonio. I'm showing that your address has been connected and has service. If this is not correct, please give us a call at 731.562.6001. If there is a secondary address you are waiting on, please let us know what it is and we will be able to provide you with an update. Thank you!
10:46AM May 22, 2022
Gail McConnell
You website is the most difficult unfriendly site I have seen in years. It takes a computer degree to figure out how to PAY MY BILL ON LINE. You folks do know this is northwest Tn not Berkeley Ca. right?
8:31AM May 23, 2022
Sarah Williams
Hi, Gail. We apologize for the issues you've had trying to pay your bill online. If you have not created an account, we will be happy to help you do that. Please contact us at 731.562.6000 and one of our Member Service Representatives will be glad to assist you. We are glad you're a Gibson Connect subscriber!
9:20PM May 13, 2022
Mack P
I believe Kentucky has passed with emergency status for rural internet. When that will happen and how much less will the cost be from Gibson's original quote???? Because it was posted by Gibson Connect even though Fulton Zone reached its required "subscribers" they stopped work for Kentucky ZONES to have a lower cost!!!!!! Since according to Gibson Connect the Fulton zone should already have their internet SERVICE !!!!!!
9:20AM May 16, 2022
Sarah Williams
Mack, while high-speed broadband is essential to our rural service area, applying for grants and trying to reduce costs to our members is also important to us. We have applied for grant funding whenever possible. Following the announcement of the broadband grants in Kentucky, we felt that it was in our members' best interest to apply for and try to attain grant dollars for the buildout in our Kentucky area. At this time, we are awaiting results from the state before we move forward. We appreciate your patience and support, and we look forward to serving you.
5:04PM May 12, 2022
MaryBeth Pickering
Any idea on when we will be connected? We have had two different crews out one hooking the box up at our house and another with the line.
11:01AM May 13, 2022
Dawn Jewell
MaryBeth, there are several steps that will have to be completed before your home is ready for internet. This includes constructing the main line fiber which is happening at this time in your area, putting a service drop to your home, placing a NID (small gray box) to make a connection, splicing the fiber at your home, and then testing the light. Once we have received word that the home is ready to be connected, our team will reach out to you and schedule it at your convenience. Thank you for your support of Gibson Connect!
8:12AM May 13, 2022
MaryBeth Pickering
3705 Church Rd Union City, TN
7:56AM May 13, 2022
Dawn Jewell
Hi, MaryBeth. Please provide me with your address so I can check on this for you. Thanks.
7:20AM May 12, 2022
Larry Clark
Can you give an connection update for 677 Lower Jackson Rd, Bells? Thanks.
3:46PM May 12, 2022
Larry Clark
Hello Sarah. Thanks for the quick response. One of your team was by here this afternoon and looked over the layout. He was very service focused!
9:13AM May 12, 2022
Sarah Williams
Hey, Larry. There was a bit of a set-back with your address, but I have spoken with our team and we should have your address ready to connect in the next 7-10 days. There are a couple of homes on Lower Jackson Road that we are working to finish; barring any unforeseen circumstances in the next few days, we expect to have you up and going in the next couple of weeks. Thank you for your patience and continued support of Gibson Connect!
8:43PM May 11, 2022
Richard Parham
Wondering when service will be connected at 9893 McConnell rd?
8:45AM May 12, 2022
Sarah Williams
Hi, Richard. At this time, we are anticipating connections to begin in the South Fulton zone sometime in June, and the majority to be largely connected by late summer. Of course, there are factors that can impact this timeline such as weather, contractor staffing and materials availability. We appreciate your support of Gibson Connect and look forward to serving you!
9:12PM May 10, 2022
Christian Comer
I had a concern about why my ping has gone up to over 100+ on all sites. I've restarted my router but my ping is still over 100+ consistently usually I get a solid 20 but all day today its been over 100.
8:40AM May 11, 2022
Sarah Williams
Hi, Christian. If you are still experiencing issues, please call us at 731.562.6001 and one of our technical support staff will be able to take a look at your account. Thank you for being a Gibson Connect subscriber!
12:23AM May 11, 2022
Christian Comer
Seems to be working normally except the only site pinging over 100 ping is google now everything else seems to be normal.